DBCT outloading berth
Project Status

Project Update

Approx. % complete as at end July 2008
Lost Time Injury Frequency Rate (LTIFR) (for 4,195,624 hours worked)
0.476

Project Status

- Engineering/Design - overall for 3 Phases

- Overall Project Completion

- Phase 1 Completion

- Phase 2/3 Completion

- Total Commitments

- Total Expenditure

- Total Site Workforce

 

100%

86.6%

100%

76.5%

$1,138,912,356

$1,051,486,298

658 people

Significant Contracts Awarded

- Design, Supply, Erect and Commission Stackers & Reclaimers (Voest Alpine)

- Row 8 Preparatory Earthworks (Golding Contractors)

- Construct Rail Receival Pit RRP3 and S11 Tunnel (Golding Contractors)

- Design, Supply and Deliver Transformers (Areva)

- Supply, Erect and Commission Inloading Conveyor System (IL3) (McConnell Dowell)

- Design, Supply and Deliver Transportable Substations (Ausco Building Systems)

- Transportable Site Buildings (ATCO Structures)

- Supply of Ambulance and First Aid Services (BLP Training and Services)

- Construct Site Dams

- Supply and Deliver Bund 5A & 6 Rail (OneSteel trading as Emrails)

- Construct Bund 5A (BMD)

- Construct Bund 6 (BMD)

- Cable Identification and Minor Electrical Site Services (O'Donnell Griffin)

- Upgrades to Stacker/Reclaimer SR5 (TEAM Engineering)

- Supply & Construct Conveyor R7 Including L1 & L2 Conveyor Extensions (Robt Stone & Co)

- Upgrades to Conveyors L1/L2/L3/L4 & Belt Feeder BF5 & BF7 Drives (Robt Stone & Co)

- Relocate Stacker/Reclaimer SR4 and Upgrade/Modify to RL2 on Bund 6 (TEAM Engineering)

- Upgrades to Conveyor R4 (McFee Pty Ltd)

- Upgrades to Shiploader SL2 (TEAM Engineering Pty Ltd)

- Marine Works - OL3 Offshore Conveyor and Berth 4 (John Holland) Phase 2/3

- Supply and Install Power System Upgrade Works (O'Donnell Griffin)

- Supply of Control System Upgrade Services (Camms)

- Site Access Roads and Auxiliary Civil Works (BMD)

- Design, Supply and Deliver Chutes (Tasman Warajay)

- Design, Supply and Deliver Conveyor Idlers (Continental Conveyor & Equipment Pty Ltd)

- Design, Supply and Deliver Conveyor Belts (Contitech)

- Design, Supply and Deliver Conveyor Drives (Hansen Transmissions)

- Design, Supply and Deliver Conveyor Pulleys (Tefco Engineering)

- Design, Supply and Deliver 33kV Indoor Circuit Breaker (Schneider Electric)

- High Voltage Cable Supply Contract (Prysmian Cables and Systems)

- Design, Supply & Deliver 11kV & 3.3kV Indoor Switchgear (ABB Australia)

- Design, Supply & Deliver Wagon Vibrator (WBM Pty Ltd)

- Design/Supply/Install/Commission Anti-Collision Sys for Yard Machines/Shiploaders (Matrikon)

- Des./Supply/Install & Commission Security Syst (Homeland National Sec. Services) formerly Chubb

- Design, Supply and Deliver Transformers (Wilson Transformers)

- Design, Supply and Deliver Transformers (Schneider Electric)

- Design, Supply and Deliver Transformers (Ampcontrol Transformers)

- Design, Supply & Deliver Slew Drives for SR5 Upgrade (Siemens)

- Upgrades to Ship Loader SL1 (Walz Construction)

- Minor Civil and Building Site Services (WH Frier Building Contractor)

- Waste Collection Site Services (JJ Richards)

- Minor Mechanical, Civil and Electrical Work on Site (DGH Engineering)

- Site Cleaning Services (Spotless)

- Piping Materials for WM1 (Tyco Water)

- Offsite Inspection and Expediting Services (Moody International)

- Design and Supply RL2 Bucket Wheel (Voest Alpine)

- Fabricate & Supply RL2 Boom (G & S Engineering)

- Supply and Deliver Drive Units for SL1 and SL2 (Siemens)

- Supply and Deliver Hagglund Drives (Hagglunds)

- Supply and Deliver Stockpile Sprays - Bunds 4A, 5A & 6 (Dowdens Pumping)

- Outloading System OL3 Reclamation Works (BMD) (Phase 2/3)

- Construct Bund 4A (BMD) Phase 2/3

- Supply and Construct Conveyors R8 and S8 (Monadelphous) Phase 2/3

- Design, Supply, Erect and Commission Stackers & Reclaimers (Voest Alpine) Phase 2/3

- Design, Supply and Deliver Conveyor Idlers (Continental Conveyor & Equipment ) Phase 2/3

- Design, Supply and Deliver Conveyor Belts (Contitech) Phase 2/3

- Design, Supply and Deliver Conveyor Drives (Hansen Transmissions) Phase 2/3

- Design, Supply and Deliver Conveyor Pulleys (Tefco Engineering) Phase 2/3

 

 

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

75%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

92%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

92%

64%

94%

100%

100%

100%

100%

Schedule
Current Forecast

                     Phase 1                      

                     Phase 2/3                   

                    

Completed 03/03/08

first quarter 09