Project Update |
Approx. % complete as at end July 2008
|
| Lost Time Injury Frequency Rate (LTIFR) (for 4,195,624 hours worked) |
0.476
|
|
Project Status - Engineering/Design - overall for 3 Phases - Overall Project Completion - Phase 1 Completion - Phase 2/3 Completion - Total Commitments - Total Expenditure - Total Site Workforce |
100% 86.6% 100% 76.5% $1,138,912,356 $1,051,486,298 658 people |
Significant Contracts Awarded - Design, Supply, Erect and Commission Stackers & Reclaimers (Voest Alpine) - Row 8 Preparatory Earthworks (Golding Contractors) - Construct Rail Receival Pit RRP3 and S11 Tunnel (Golding Contractors) - Design, Supply and Deliver Transformers (Areva) - Supply, Erect and Commission Inloading Conveyor System (IL3) (McConnell Dowell) - Design, Supply and Deliver Transportable Substations (Ausco Building Systems) - Transportable Site Buildings (ATCO Structures) - Supply of Ambulance and First Aid Services (BLP Training and Services) - Construct Site Dams - Supply and Deliver Bund 5A & 6 Rail (OneSteel trading as Emrails) - Construct Bund 5A (BMD) - Construct Bund 6 (BMD) - Cable Identification and Minor Electrical Site Services (O'Donnell Griffin) - Upgrades to Stacker/Reclaimer SR5 (TEAM Engineering) - Supply & Construct Conveyor R7 Including L1 & L2 Conveyor Extensions (Robt Stone & Co) - Upgrades to Conveyors L1/L2/L3/L4 & Belt Feeder BF5 & BF7 Drives (Robt Stone & Co) - Relocate Stacker/Reclaimer SR4 and Upgrade/Modify to RL2 on Bund 6 (TEAM Engineering) - Upgrades to Conveyor R4 (McFee Pty Ltd) - Upgrades to Shiploader SL2 (TEAM Engineering Pty Ltd) - Marine Works - OL3 Offshore Conveyor and Berth 4 (John Holland) Phase 2/3 - Supply and Install Power System Upgrade Works (O'Donnell Griffin) - Supply of Control System Upgrade Services (Camms) - Site Access Roads and Auxiliary Civil Works (BMD) - Design, Supply and Deliver Chutes (Tasman Warajay) - Design, Supply and Deliver Conveyor Idlers (Continental Conveyor & Equipment Pty Ltd) - Design, Supply and Deliver Conveyor Belts (Contitech) - Design, Supply and Deliver Conveyor Drives (Hansen Transmissions) - Design, Supply and Deliver Conveyor Pulleys (Tefco Engineering) - Design, Supply and Deliver 33kV Indoor Circuit Breaker (Schneider Electric) - High Voltage Cable Supply Contract (Prysmian Cables and Systems) - Design, Supply & Deliver 11kV & 3.3kV Indoor Switchgear (ABB Australia) - Design, Supply & Deliver Wagon Vibrator (WBM Pty Ltd) - Design/Supply/Install/Commission Anti-Collision Sys for Yard Machines/Shiploaders (Matrikon) - Des./Supply/Install & Commission Security Syst (Homeland National Sec. Services) formerly Chubb - Design, Supply and Deliver Transformers (Wilson Transformers) - Design, Supply and Deliver Transformers (Schneider Electric) - Design, Supply and Deliver Transformers (Ampcontrol Transformers) - Design, Supply & Deliver Slew Drives for SR5 Upgrade (Siemens) - Upgrades to Ship Loader SL1 (Walz Construction) - Minor Civil and Building Site Services (WH Frier Building Contractor) - Waste Collection Site Services (JJ Richards) - Minor Mechanical, Civil and Electrical Work on Site (DGH Engineering) - Site Cleaning Services (Spotless) - Piping Materials for WM1 (Tyco Water) - Offsite Inspection and Expediting Services (Moody International) - Design and Supply RL2 Bucket Wheel (Voest Alpine) - Fabricate & Supply RL2 Boom (G & S Engineering) - Supply and Deliver Drive Units for SL1 and SL2 (Siemens) - Supply and Deliver Hagglund Drives (Hagglunds) - Supply and Deliver Stockpile Sprays - Bunds 4A, 5A & 6 (Dowdens Pumping) - Outloading System OL3 Reclamation Works (BMD) (Phase 2/3) - Construct Bund 4A (BMD) Phase 2/3 - Supply and Construct Conveyors R8 and S8 (Monadelphous) Phase 2/3 - Design, Supply, Erect and Commission Stackers & Reclaimers (Voest Alpine) Phase 2/3 - Design, Supply and Deliver Conveyor Idlers (Continental Conveyor & Equipment ) Phase 2/3 - Design, Supply and Deliver Conveyor Belts (Contitech) Phase 2/3 - Design, Supply and Deliver Conveyor Drives (Hansen Transmissions) Phase 2/3 - Design, Supply and Deliver Conveyor Pulleys (Tefco Engineering) Phase 2/3
|
100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 75% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 92% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 92% 64% 94% 100% 100% 100% 100% |
Schedule |
Current Forecast |
|
Phase 1 Phase 2/3
|
Completed 03/03/08 first quarter 09 |