Modifications and enhancements are proposed to all major terminal elements of inloading, stockyard and outloading.
The additional infrastructure to be installed comprises the following:
- a complete new third inloading system including rail loop, and dump station
- expansion of the Stockyard with 3 additional machinery bunds, 2 new stockpile rows and 4 additional stacking/reclaiming machines
- a complete third outloading string feeding the 3 existing berths
- an optional fourth berth; and
- additional controls to reduce the impact of noise and dust emissions
The current terminal configuration, with the above expansion scope components shown, can be seen in an animated presentation